The concrete pour was completed in a single day using a pump, despite challenging weather conditions. Struck and collected 17 days later, the project delivered a robust finished wall, leaving both S & A Shanks Ltd and Patersons Quarries Ltd highly satisfied with the outcome.
Creative formwork solution creates safe storage
Dumbuckhill Quarry, Dumbarton
Project Overview
| Location |
|
|---|---|
| Sector | Building |
| Products |
Dumbuckhill Quarry in Dumbarton, Scotland required a free standing wall structure for the safe storage of aggregate, sand and other quarrying equipment on site.
Our solution
The design required one hinged corner to allow for the footprint of the pour in order for the bays to be constructed. The system was built by four operatives and assembled in 3m high by 2.7m wide panels.
The assembled unit was lifted using 2 number Frami lifting hooks connected to 2 leg chain, which was attached to the forks on a telehandler.
Learn more about Formwork
This particular concrete pour started in early November, and was stripped and collected 17 days later, leaving a solid concrete wall for storing materials. The pour was completed in one day using a concrete pump; as the site location is very open it was affected by wind and rain which proved more challenging.
From the initial enquiry to close of business, the customer and client Patersons Quarries Ltd were delighted with our service.
Get in touchProject images
Related news and projects
- Project
- Isle of Wight
Formwork solution enables construction of vital concrete structure
- Project
- International Bomber Command Centre, Lincoln
War memorial creation calls for Frami panel system
Give us a call
For all project specific design and technical enquiries, please contact your local service team
Send us an email
If you want to talk to us about your project, send us an email and a brief outline of how we can help and we’ll be in touch
[email protected]
“Having used the Frami Panel System on previous contracts, we were impressed with the ease and speed of construction and removal, and also the continued excellent service provided by the Mabey Hire team.”